Essential road upgrades to Maritana Street

The City is making significant improvements to Maritana Street as part of our Roads Renewal Program, with works scheduled for June 2025. These important upgrades will enhance the driving experience and ensure greater road durability for years to come.

The works will focus on high-traffic areas within the Kalgoorlie CBD and will involve profiling, sealing, concreting, kerbing, and asphalt works.

The City’s contractors will liaise with businesses throughout the project to ensure minimal disruption and continued accessibility to customers. On-road parking will not be permitted in the scheduled works are, parking will be available outside the immediate worksite area.

Work Schedule

5th June 2025

  • Job 1: Maritana Street (Egan to Hannan, Both Sides) – Profiling
    • This section will be closed to traffic. Please follow designated detour routes until profiling is complete, after which the section will be reopened to traffic.
  • Job 2: Maritana Street (Hannan to Brookman, Both Sides) – Profiling
    • While Job 1 is underway, this section will remain open to traffic; however, car parking spaces will be closed.
    • Upon completion of Job 1’s profiling, the crew will commence profiling Job 2.
    • During Job 2 profiling, this section will be closed to traffic, and detours will be in place. Job 1 will be reopened to traffic at this time.

6th June 2025

  • Job 1: Maritana Street (Egan to Hannan, Both Sides) – Sealing
    • This section will be closed to traffic. Please follow detour routes until sealing is complete, after which the section will be reopened to traffic.
  • Job 2: Maritana Street (Hannan to Brookman, Both Sides) – Sealing
    • While Job 1 is underway, this section will remain open to traffic; however, car parking spaces will be closed.
    • Upon completion of Job 1’s sealing, the crew will commence sealing Job 2.
    • During Job 2 sealing, this section will be closed to traffic, and detours will be in place. Job 1 will be reopened to traffic at this time.

9th June 2025

  • Job 1: Maritana Street (Egan to Hannan, Both Sides) – Asphalting
    • This section will be closed to traffic. Please follow detour routes until asphalting is complete, after which the section will be reopened to traffic.

10th–11th June 2025

  • Job 2: Maritana Street (Hannan to Brookman, Both Sides) – Asphalting
    • This section will be closed to traffic over two days. Please follow detour routes until asphalting is complete, after which the section will be reopened to traffic.

Additional Notes:

  • At the conclusion of each day’s work, the respective work areas will be reopened to traffic.
  • At no point will both Job 1 and Job 2 be closed to traffic simultaneously. Only parking spaces will be restricted in the section open to traffic while works are underway in the other section.

Phase 2


For more information

See our FAQs section or contact us on 08 9021 9600 and mailbag@ckb.wa.gov.au