A smoother road for Burt Street
The City will be making significant improvements to Burt Street as part of our Roads Renewal Program, with works scheduled from late November to January. These important upgrades will enhance the driving experience and ensure greater road durability for years to come.
The works will focus on several high-traffic areas within the Boulder CBD and will involve stabilising, kerbing, asphalt works, and roundabout improvements.
The City’s contractors will liaise with business throughout the project to ensure minimal disruption and continued accessibility to customers. Off-street parking will be available on the opposite side of the street and traffic will continue to flow throughout the works period.
Project Stages
Stage One: Burt St - South Side - Lane to Hamilton St
- Dates: 25 November - 19 December 2024
- Type of Work: Profiling Parking Bays, Stabilisation, Seal, Asphalt
Stage 2: Burt St - North Side - Lane to Hamilton St
- Dates: December 26 November - 21 December, 2024
- Type of Work: Profiling Parking Bays, Stabilisation, Seal, Asphalt
Stage 3: Burt St - North Side - Brookman to Lane St
- Dates: 27 November - 7 January, 2025
- Type of Work: Profiling Parking Bays, Stabilisation, Seal, Asphalt
Stage 4: Burt St - South Side - Brookman to Lane St
- Dates: 28 November - 9 January, 2025
- Type of Work: Profiling Parking Bays, Stabilisation, Seal, Asphalt
Stage 5: Burt St/Lane St Roundabout
- Dates: 2 December - 20 January, 2025
- Type of Work: Demolition, Stabilisation, Seal, Asphalt, Kerb Rebuild, Concrete and Spray Application
Stage 6: Burt St/Hamilton St Roundabout
- Dates: 4 December - 21 January, 2025
- Type of Work: Demolition, Stabilisation, Seal, Asphalt, Kerb Rebuild, Concrete and Spray Application
For more information
See our FAQs section or contact us on 08 9021 9600 and mailbag@ckb.wa.gov.au