Terminal Roadworks
About the project
As part of ongoing improvements at the airport, the City is undertaking resurfacing works on the pick-up and drop-off road in front of the terminal between 12-28 October 2024.
These proactive repairs ensure the long-term sustainability of the road, preventing further damage, and avoiding the need for costly repairs in the future.
The works will focus on the pick-up and drop-off loop directly outside the airport’s arrivals and departures area, which is exposed to wear and tear due to the high volumes of daily traffic.
Project dates:
- Start Date: 12 October 2024
- Completion Date: 28 October 2024
What you need to know:
To minimise disruptions, a comprehensive traffic management plan has been developed, and the majority of work will take place outside of peak periods.
Temporary relocation of:
- Pick-Up and Drop-Off Area: The two-minute pick-up and drop-off zone will be relocated to the main public car park.
- Taxi Bays: Taxi bays will be temporarily relocated to the main public car park.
- Bus Zone: The bus area will be temporarily relocated to the long-term car park.
Other important information:
- Pedestrian Access: Temporary walkways will be constructed outside the arrivals and departures doors, ensuring safe pedestrian access across the work zones.
- General Parking: Paid parking will still be open and available as per normal.
- Disabled Parking: Will still be unaffected and available to those with ACROD permits
Those travelling or visiting the airport are asked to allow extra time and follow all directional signage.