Phase Two - Keenan Street to Maritana Street Shared Path Project
The City of Kalgoorlie Boulder is planning for the construction of a Shared Use Path (SUP) on Maritana - Piccadilly - Keenan Street as shown in the drawing in the Document Library section of this page.
About the funding
The City of Kalgoorlie-Boulder has received two Department of Transport’s Western Australian Bicycle Network (WABN) grants, to extend the city’s Cycling Network:
- Phase Two - Keenan Street to Maritana Street Shared User Path Project
Stage 1
- Project Cost: $400,000
- City Contribution: $200,000
- DoT Contribution: $200,000
Breakdown:
- Design Works - 2022/23 FY - $20,000
- Construction Works - June 2025 - $180,000
Stage 2
- Planning – Design completed and planned to complete construction on FY2025/26
- Project Cost: $423900
- Grant Value: $211,950
Public feedback
Have your say on the detailed designs and features of the shared user path. Download the design under the document library on this page and complete the survey below.
This survey closed on Friday 16 April.