Phase One - Lane Street and Forrest Street Shared User Path Project
The City of Kalgoorlie-Boulder engaged the services of Civilstorm to commence the design phase of the extension of the City’s Cycling Network with a shared-use path (SUP).
About the funding
The City of Kalgoorlie-Boulder has received two Department of Transport’s Western Australian Bicycle Network (WABN) grants, to extend the city’s Cycling Network in two locations
Phase One - Lane Street and Forrest Street Shared User Path Project
- Project Cost: $285,687
- City Contribution: $170,687
- DoT Contribution: $125,0000
Breakdown:
- Design Works - 2021/23 FY - $10,000
- Construction Works - 2022/23 FY - $115,000
Current Project Status
Works are scheduled for completion by May 2024